Tutorial Info
- Program:
- Version:
- Difficulty:
- Time to Complete: 10 minutes
It turns out that people like pictures. Yes, that’s right, we love pictures….and we love the Gantt Chart. What makes the Gantt Chart so essential is that it simplifies something that is complex. It gives us a snapshot and a trend that our brain can digest rather than just text and numbers.
Getting the Gantt Chart to look the way you need it is a really key skill for Primavera users.
Recently someone asked me how to shade non-work time on the Activity Gantt Chart in Primavera P6. They wanted to show clearly what days are workable and which are non-working on the Gantt Chart in P6.

It turns out it’s pretty simple to set but not terribly intuitive in Primavera, as some things are, which is why we post tutorials.
You can control how the Gantt Chart is shaded by setting the appropriate “Default Calendar“.
- From the “Enterprise” menu, select “Calendars“.
- Ensuring you have “Global” selected at the top, pick a default calendar from this screen by placing a checkmark next to it.

Although the Default Calendar serves a few purposes in P6, it’s also used to set the shading on the Gantt Chart. Of course, what is shaded as non-work on the P6 Gantt depends on what level of zoom you have set your timescale. Set the timescale to “Week / Day 1” or ”Week / Day 2” and you will see shading on the Gantt chart (as long as the default calendar has non-work days set). For most cases you will likely have a Global Calendar in the list that is similar or matches your project’s main calendar.
But what if your project uses a “Project Calendar”?
There’s no easy fix in this case. You could create a copy of your Project Calendar and convert it to a Global Calendar, then make it the Default Calendar. Otherwise, you’ll have to pick a Global Calendar to use for shading. You can also turn shading right off by choosing a 24 x 7 calendar with no non-work days.
Now you have one more tool to paint a pretty picture of your project plan.












3 Responses
[...] is important! Last post, we showed you the nuances of shading non-work time on the Primavera Gantt Chart. Today we’re uncovering some more nuances of that essential Gantt [...]
Great tip! Personally, I never try to show this amount of detail in my timescales (even weekly detail is a bit much for a project duration of over a year) but I had a client who wanted to see holidays and weekends shaded.
One observation: As long as the default calendar MATCHES the project calendar you are using it really does not matter if in fact you are using a global calendar in your schedule. I do not use or recommend global calendars for projects because other users can potentially modify them.
Having the shading always being controlled by the default calendar will of course be confusing for anyone who uses many different types of calendars. As a demonstration, I opened up a 5-day workweek project and watched the shading change as I picked different default global calendars.
A potential drawback: many construction projects use more than one calendar. Concrete curing, for example, is a 7-day calendar, while the work is ususally a 5-day calendar. The shading can only apply to one calendar and not all the ones being used. The owner might assume based on shading that all activities are governed by a single calendar.
However, since P6 took away our ability to PRINT calendars, this is the only way I know of to show someone the details of the calendar I am using, global or otherwise. For this reason alone I like this shading option.
Can we use Primavers for Earned Value Management? What dype of Percent complete would you use for good EVM?